Similar to PIPE2D-912, please provide the plan for Princeton for data acquisition for the May 2022 run, the expected time needed for each activity, if it's a daytime activity etc. and the priority for each activity
This is expected to include:
- Dot-crossing
- Dot-roach
- Isolated fibers for PSF modelling
- Isolated fibers for odd/even fiber profile modelling
- Dithered flats.
- is blocked by
-
PIPE2D-1025 estimate flux from PFI cont. lamp and HSC lamp, for PIPE2D-1018
- Done
- relates to
-
PIPE2D-1077 Plan for data acquisition during Sep 2022 run
- Done
-
INSTRM-1392 Determine blackspot positions on PFI at different elevation angles