[PIPE2D-879] Repeat data acquisition for DCB in blue with HgAr Created: 05/Aug/21  Updated: 02/Oct/21  Resolved: 02/Oct/21

Status: Done
Project: DRP 2-D Pipeline
Component/s: None
Affects Version/s: None
Fix Version/s: None

Type: Task Priority: Normal
Reporter: ncaplar Assignee: ncaplar
Resolution: Done Votes: 0
Labels: None
Remaining Estimate: Not Specified
Time Spent: Not Specified
Original Estimate: Not Specified

Issue Links:
Blocks
blocks PIPE2D-789 Reduce data described in PIPE2D-788 Done
Story Points: 2

 Description   

While taking data with HgAr lamp during June/July acquisition I made a mistake and I took the data in the same fashion as with noble gas lamps. Given that the flux of HgAr lamp is a nonlinear function of time, I have seriously overexposed the defocused data, and achieved very low flux in the focused data. This data acquisition has to be repeat, either by using a shutter or by carefully modifying exposure times. During SPS telecon on Wen, August 4 2021, it has been projected that the possibility for this work might exist during end of August, beginning of September. 



 Comments   
Comment by ncaplar [ 05/Aug/21 ]

Part of this analysis could be done with available Neon data. 

Comment by ncaplar [ 08/Sep/21 ]

As discussed in #commisioning, it might be possible to take some data at the end of this week (which started on September 6)

Generated at Sat Feb 10 15:59:16 JST 2024 using Jira 8.3.4#803005-sha1:1f96e09b3c60279a408a2ae47be3c745f571388b.