[PIPE2D-668] Support ISR processing for NIR data Created: 05/Dec/20  Updated: 28/Oct/22  Resolved: 16/Oct/22

Status: Done
Project: DRP 2-D Pipeline
Component/s: None
Affects Version/s: None
Fix Version/s: None

Type: Task Priority: Normal
Reporter: hassan Assignee: rhl
Resolution: Done Votes: 0
Labels: None
Remaining Estimate: Not Specified
Time Spent: Not Specified
Original Estimate: Not Specified

Issue Links:
Relates
relates to PIPE2D-882 Support reading PF?B files as rawb an... Open
relates to PIPE2D-1093 Rename ccdExposure to exposure in gen... Open
relates to PIPE2D-1102 Import DM-35718 solution for Gen2 dat... Done
relates to INSTRM-1700 have drpActor ingest and detrend NIR ... Done
relates to PIPE2D-1088 Add PFSB-compliant NIR data to weeklies Done
relates to PIPE2D-1095 Fix w.2022.42 weekly test failure Done
relates to INSTRM-1563 Support LAM NIR testing effort Open
Story Points: 2
Sprint: 2DDRP-2021 A, 2DDRP-2021 A 7, 2DDRP-2021 A12, 2DDRP-2022 A, 2DDRP-2022 E, 2DDRP-2022 F
Reviewers: price

 Description   

The 2D DRP needs to perform Instrument Signature Removal (ISR) on NIR data.

This is a placeholder ticket, to capture this work. Details will be added as comments and related tickets in due course.



 Comments   
Comment by hassan [ 14/Jan/22 ]

Waiting on gimbalator data.

Comment by hassan [ 18/Aug/22 ]

This can be closed. Need add RHL's report to this prior to closing. Future work will be subject to separate tickets.

Comment by hassan [ 18/Aug/22 ]

Report by RHL and C. Loomis that describes the software implemented for this ticket is available here: https://sumire.pbworks.com/w/file/fetch/149867184/princeton-software_NCU1review20220722.pdf

Comment by hassan [ 18/Aug/22 ]

In discussions during ICS/DRP+SpS telecon 2022-08-17, ticket considered closed. Report linked.

Comment by hassan [ 15/Sep/22 ]

Changes unfortunately not yet committed to master. Ticket subsequently reopened. With Sep 2022 engineering run looming, suggest to delay merging to master till after that run, or at least till the DRP software for the Sep run is tagged.

Comment by arnaud.lefur [ 08/Oct/22 ]

Might be the right moment to merge right ?
LAM is about to take actual data on N2.

Comment by hassan [ 08/Oct/22 ]

I think so. price? Any comments?

Comment by price [ 08/Oct/22 ]

I don't see pull requests. Has this been reviewed? Is it up-to-date with master?

Comment by hassan [ 13/Oct/22 ]

Additional changes made to support integration tests and weekly builds. Ready for review.

Comment by rhl [ 14/Oct/22 ]

Responded to (almost all) comments.  Didn't squash commits, if necessary this could be done tomorrow, but I think that the code and doc changes are there.

Comment by hassan [ 16/Oct/22 ]

Integration test passes and local weekly build run. Merged to master.