[PIPE2D-626] Estimate the exposure times for arc lines after attenuator readjustment with SM1 on Subaru Created: 26/Aug/20  Updated: 27/Aug/20  Resolved: 27/Aug/20

Status: Done
Project: DRP 2-D Pipeline
Component/s: None
Affects Version/s: None
Fix Version/s: None

Type: Task Priority: Normal
Reporter: ncaplar Assignee: ncaplar
Resolution: Done Votes: 0
Labels: None
Remaining Estimate: Not Specified
Time Spent: Not Specified
Original Estimate: Not Specified

Attachments: PNG File Flux levels.png    
Story Points: 1

 Description   

Estimate the optimal time for different lines at SM1 at Subaru, after attenuator got readjusted on August 25, 2020. Rehash of PIPE2D-529 and PIPE2D-324.



 Comments   
Comment by ncaplar [ 27/Aug/20 ]

I did a small analysis with the custom data acquired on August 26, 2020. The results are summarized in Flux_levels.png image. 

Copying from what I wrote on slack in #commisioning channel:

We are saturating all lamps at 5sec, getting close to saturation for all lamps with 3sec - although I have not been able to take data with Krypton (I tried 3 times). HgAr saturated at 1 second already. There is certainly still some jumping of effective expTime, i.e., I see that actual expTime does not correspond to the requested one. We discussed the flux during SPS telecon today, we probably want to have lower flux so that uncertainty of cca 1 sec in expTime that we see is not affecting us that much. 