[PIPE2D-1219] Measure and correct electronic crosstalk Created: 13/May/23  Updated: 13/May/23  Resolved: 13/May/23

Status: Done
Project: DRP 2-D Pipeline
Component/s: None
Affects Version/s: None
Fix Version/s: None

Type: Story Priority: Normal
Reporter: price Assignee: price
Resolution: Done Votes: 0
Labels: None
Remaining Estimate: Not Specified
Time Spent: Not Specified
Original Estimate: Not Specified


 Description   

Electronic crosstalk is visible in r1 and r3, and it complicates understanding of the background (PIPE2D-1212). Measure the effect, and remove it.



 Comments   
Comment by price [ 13/May/23 ]

Work imported from tickets/PIPE2D-1148.
Integration tests pass.