[INSTRM-998] Write SPS software test report following software migration Created: 06/Jun/20  Updated: 13/Aug/21  Resolved: 13/Aug/21

Status: Done
Project: Instrument control development
Component/s: None
Affects Version/s: None
Fix Version/s: None

Type: Task Priority: Normal
Reporter: hassan Assignee: Unassigned
Resolution: Done Votes: 0
Labels: None
Remaining Estimate: Not Specified
Time Spent: Not Specified
Original Estimate: Not Specified

Story Points: 2

 Description   

Write the above report, similarly to that for the SM1 pre-shipping tests in Oct 2019.



 Comments   
Comment by hassan [ 13/Aug/21 ]

Report has been written and added to pbworks: https://sumire.pbworks.com/w/file/140442921/PFS-SPS-LAMTRE1074_SW-TestReport.pdf