[INSTRM-952] Write SPS software test case document for migration post SM1 AIT Created: 16/Apr/20 Updated: 30/May/20 Resolved: 30/May/20 |
|
| Status: | Done |
| Project: | Instrument control development |
| Component/s: | None |
| Affects Version/s: | None |
| Fix Version/s: | None |
| Type: | Story | Priority: | Normal |
| Reporter: | hassan | Assignee: | hassan |
| Resolution: | Done | Votes: | 0 |
| Labels: | SPS | ||
| Remaining Estimate: | Not Specified | ||
| Time Spent: | Not Specified | ||
| Original Estimate: | Not Specified | ||
| Issue Links: |
|
||||||||
| Story Points: | 4 | ||||||||
| Sprint: | SM1PD-2020 G | ||||||||
| Description |
|
At the end of the SM1 AIT test campaign performed by the LAM team at Subaru, the SPS ICS software will be migrated to make use of the IIC actor and opDB. Using the pre-shipping SM1 test case document as a basis, write a new document that enables: 1. Validation of the spsait software system before migration (to ensure that we are ready to migrate) |
| Comments |
| Comment by hassan [ 30/May/20 ] |
|
Skeleton completed. |