[INSTRM-901] Establish a mechanism to save the convergence test results in opDB Created: 19/Feb/20  Updated: 01/Apr/20  Resolved: 01/Apr/20

Status: Done
Project: Instrument control development
Component/s: spt_operational_database
Affects Version/s: None
Fix Version/s: None

Type: Task Priority: Normal
Reporter: Kiyoto Yabe Assignee: Kiyoto Yabe
Resolution: Done Votes: 0
Labels: opDB
Remaining Estimate: Not Specified
Time Spent: Not Specified
Original Estimate: Not Specified

Issue Links:
Relates
relates to INSTRM-905 Update opDB schema for PFI works at ASRD Done

 Description   

We would like to save the results of the convergence test in opDB. Make sureĀ  that such info can be traceable in the current scheme. We may need to prepare a separate table including e.g. SNR for the convergence test.