[INSTRM-581] SM1 final software validation (R, B and N available) Created: 19/Dec/18  Updated: 03/Oct/19  Due: 24/May/19  Resolved: 03/Oct/19

Status: Won't Fix
Project: Instrument control development
Component/s: None
Affects Version/s: None
Fix Version/s: None

Type: Epic Priority: Normal
Reporter: hassan Assignee: Unassigned
Resolution: Won't Fix Votes: 0
Labels: SM1
Remaining Estimate: Not Specified
Time Spent: Not Specified
Original Estimate: Not Specified

Epic Name: R, B and N software validation

 Comments   
Comment by hassan [ 10/Jan/19 ]

Currently hard deadline for all S/W to be implemented for SM1 is 6 June 2019 (SM1 testing in cold chamber). Assign due date for final testing to 24 May in order to have a contingency.