[INSTRM-1819] Punch List for Run 09 (December 2022) Created: 08/Dec/22  Updated: 04/Jan/23  Resolved: 04/Jan/23

Status: Done
Project: Instrument control development
Component/s: None
Affects Version/s: None
Fix Version/s: None

Type: Task Priority: Normal
Reporter: yuki.moritani Assignee: Unassigned
Resolution: Done Votes: 0
Labels: EngRun
Remaining Estimate: Not Specified
Time Spent: Not Specified
Original Estimate: Not Specified

Sprint: PreEngRun09Dec

 Description   

Here is a test and check list for software updates before coming the engineering run (2022/12/15-18). Note that all the software should be tagged and implemented at the summit/Hilo system, except for agccActor agccAcrot will be updated after the test with MELCO.

  • AG centroiding INSTRM-1789, size measurement INSTRM-1773, and configuration INSTRM-1784
    • Run agccActor on Yoshida's simulator (Yoshida, Karr)
  • Cobra convergence
    • Run cobra convergence and restart and check is movement is recorded correctly (Yan, INSTRM-1791)
    • Check fps keywords (Yan, INSTRM-1419)
  • groupID 
    • Check if Gen2 gets correct groupID from PFS (Loomis, INSTRM-1719)
    • Check if Gen2 commands groups ditherring data (Koshida, Takagi, INSTRM-1720)
  • FITS
    • Check if all required headers (see INSTRM-1444) are correctly populated (Loomis, FITS committee?)
  • Confirm CALIB PIPE2D-1122, PIPE2D-1132 (Siddiqui, Price)


 Comments   
Comment by hassan [ 04/Jan/23 ]

Ticket no longer valid as Dec 2022 Run 09 has been concluded.